We are new to ADUs by choice, not by accident. This page is the record: every build, stage by stage, with the photos and dates as they happen. No stock imagery.

Detached ADU · Santa Clara County

Detached ADU, ground-up

Our first ADU as Bayfront ADU: a detached, single-storey unit on a new stem-wall foundation behind an existing home. Foundation, floor system, rough utilities, framing and weather barrier are done; stucco, interiors and landscaping are next.

  • Detached, single storey
  • Stem-wall foundation, framed floor deck
  • Separate utility rough-in
  • Stucco exterior, black window frames

In progress

About 75% built

CSLB #1131251 · DRE #02007206

Build log

  1. Floor joists framed over a new stem-wall foundation

    01 · Date to follow

    Foundation & floor system

    Engineered stem walls poured, then the floor deck framed and squared to the plans.

  2. Plumbing rough-in running through the floor joists

    02 · Date to follow

    Utilities roughed in

    Water, waste and electrical set through the joists before the subfloor closed it up.

  3. Walls sheathed in plywood with windows installed

    03 · Date to follow

    Framed, sheathed, glazed

    Walls up, roof on, windows flashed and set. Framing inspection passed.

  4. ADU roofed and wrapped in weather barrier, ready for stucco

    04 · Date to follow

    Roof and weather barrier

    Roofing on and the building wrapped, ready for lath and stucco.

Who is building it

Sam Saidian and Brad Pickens are on every job. About us →

Verify us

Look up the licence at CSLB (#1131251) and the broker licence at DRE (#02007206). Insurance certificates on request.